165,000 SF Upfit of existing shell space
Structural Steel upgrades to support new roof-top mechanical equipment
Full MEP package to support production areas and Automated Robotics Storage Warehouse
16 HVAC RTU’s installed
Security, Telecom/IT, AV package
BMS installation and commissioning
7,000 SF office buildout
Added 4000amp service and distribution
200KW Generator with 2×300 amp ATS
Exterior site improvements
Fast-track – 6-month schedule (improved by 1 month)